Master Cors
| Project | Project num | Customer | Cor num | Date | Amount | Description | Co Amount Approvel | Accept/Reject | Signed Co | Billed to PayApp# | Comments | Active/Complete | ||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Project | Project num | Customer | Cor num | Accept/Reject | Date | Amount | Description | Co Amount Approvel | Signed Co | Billed to PayApp# | Comments | Active/Complete | ||
| Project Azalea | 26128 | Allegheny | 1 | Accepted | 7/1/2026 | 500 | 500 | Complete | ||||||
| Harrison HS | 24117 | Swinerton | 1 | VOID | 5/2/2025 | $ 300.00 | HW changes | |||||||
| Harrison HS | 24117 | Swinerton | 2 | Accepted | 5/8/2025 | $ 1,650.00 | 27 additional fire rated doors | $ 16,520.00 | 1 | |||||
| Harrison HS | 24117 | Swinerton | 3 | Pending | 4/3/2026 | $ 18,400 | Revision 21 changes | |||||||
| Chapel Hill HS | 24123 | Gilbane | 1 | Accepted | 3/24/2025 | $ 4,640.00 | Addendum 2 changes | $ 4,640.00 | 1 | |||||
| Chapel Hill HS | 24123 | Gilbane | 2 | Accepted | 1/20/2026 | $ 10,180.00 | Remove 13 existing FRP doors | $ 10,180.00 | 3 | |||||
| QTS ATL2 DC10 | 25102 | DFH Commercial | 1 | Accepted | 2/11/2025 | $ 4,500.00 | Maintenance Blg 8 leafs | $ 4,500.00 | ||||||
| QTS ATL2 DC10 | 25102 | DFH Commercial | 2 R.1 | Accepted | 10/9/2025 | $ 27,300.00 | Installation of 17 single 1 pair of temp doors | $ 27,300.00 | ||||||
| QTS ATL2 DC10 | 25102 | DFH Commercial | 3 | Accepted | 5/22/2025 | $ 650.00 | FW license | $ 650.00 | ||||||
| QTS ATL2 DC10 | 25102 | DFH Commercial | 4 | Accepted | 5/30/2025 | $ 4,099.00 | Frame inventory | $ 4,099.00 | ||||||
| QTS ATL2 DC10 | 25102 | DFH Commercial | 5 R.3 | Accepted | 8/22/2025 | $ 500.00 | Repair damaged HM frames | $ 500.00 | ||||||
| QTS ATL2 DC10 | 25102 | DFH Commercial | 6 R.1 | Accepted | 12/23/2025 | $ 700.00 | 2180 changed from Single to Pair | $ 700.00 | ||||||
| QTS ATL2 DC10 | 25102 | DFH Commercial | 7 | Accepted | 3/9/2026 | $ 1,900.00 | Supply and install 26 roll-up door brackets | $ 1,900.00 | ||||||
| QTS ATL2 DC10 | 25102 | DFH Commercial | 8 | Pending | 3/13/2026 | $ 750.00 | Undercut three leafs | |||||||
| QTS ATL2 DC10 | 25102 | DFH Commercial | 9 | Pending | 3/20/2026 | $ 80.00 | Drill hole and install viewers | |||||||
| QTS ATL2 DC10 | 25102 | DFH Commercial | 10 | Pending | 5/19/2026 | $ 1,450.00 | Addition of opening 1244A | |||||||
| Clemson CVM | 25106 | Turner Construction | 1 | Rejected | 3/17/2025 | $ 30,260.00 | Barn doors | |||||||
| Clemson CVM | 25106 | Turner Construction | 1 | Rejected | 3/17/2025 | $ 30,260.00 | Barn doors | |||||||
| Clemson CVM | 25106 | Turner Construction | 2 | Accepted | 3/12/20225 | $ (4,625.00) | 1st floor shell | $ (4,625.00) | 1 | |||||
| Clemson CVM | 25106 | Turner Construction | 2 | Accepted | 3/12/20225 | $ (4,625.00) | 1st floor shell | $ (4,625.00) | 1 | |||||
| Clemson CVM | 25106 | Turner Construction | 3 | Accepted | No impact | |||||||||
| Clemson CVM | 25106 | Turner Construction | 3 | Accepted | No impact | |||||||||
| Clemson CVM | 25106 | Turner Construction | 4 | Accepted | 9/23/2025 | $ (140.88) | Addition of Wood Door 125 | $ (141.00) | 2 | |||||
| Clemson CVM | 25106 | Turner Construction | 4 | Accepted | 9/23/2025 | $ (140.88) | Addition of Wood Door 125 | $ (141.00) | 2 | |||||
| Clemson CVM | 25106 | Turner Construction | 5 | Pending | 3/11/2026 | $ 3,300.00 | Farm Animal ASI #07 | |||||||
| Clemson CVM | 25106 | Turner Construction | 5 | Pending | 3/11/2026 | $ 3,300.00 | Farm Animal ASI #07 | |||||||
| Clemson CVM | 25106 | Turner Construction | 6 | Pending | 3/12/2026 | $ 2,500.00 | Install 33 edge guards | |||||||
| Clemson CVM | 25106 | Turner Construction | 6 | Pending | 3/12/2026 | $ 2,500.00 | Install 33 edge guards | |||||||
| Clemson CVM | 25106 | Turner Construction | 7 | Rejected | 4/9/2026 | $ 2,000.00 | Additional MOB | |||||||
| Clemson CVM | 25106 | Turner Construction | 7 | Rejected | 4/9/2026 | $ 2,000.00 | Additional MOB | |||||||
| Clemson CVM | 25106 | Turner Construction | 8 | Accepted | 4/15/2026 | $ 580.00 | T&M prep work for ambulatory wood doors | |||||||
| Clemson CVM | 25106 | Turner Construction | 8 | Accepted | 4/15/2026 | $ 580.00 | T&M prep work for ambulatory wood doors | |||||||
| Clemson CVM | 25106 | Turner Construction | 9 | Pending | 4/27/2026 | $ 2,000.00 | Additional MOB | |||||||
| Clemson CVM | 25106 | Turner Construction | 9 | Pending | 4/27/2026 | $ 2,000.00 | Additional MOB | |||||||
| Clemson CVM | 25106 | Turner Construction | 10 | Pending | 6/4/2026 | $ 2,000.00 | Door modifications | |||||||
| Clemson CVM | 25106 | Turner Construction | 10 | Pending | 6/4/2026 | $ 2,000.00 | Door modifications | |||||||
| Carroll County Administration Building | 25108 | Unified Doors and Hardware | 1 R.1 | Accepted | 5/21/2025 | $ 2,300.00 | Welding of exterior frames needing flush anchors | $ 2,300.00 | ||||||
| Carroll County Administration Building | 25108 | Unified Doors and Hardware | 2 | Accepted | 7/11/2025 | $ 1,460.00 | Adjust strike prep | $ 1,460.00 | JF1479-23A | |||||
| Carroll County Administration Building | 25108 | Unified Doors and Hardware | 3 | Accepted | 7/28/2025 | $ 1,300.00 | Temp doors | $ 1,300.00 | JF1479-25A | |||||
| Carroll County Administration Building | 25108 | Unified Doors and Hardware | 4 | Accepted | 9/25/2025 | $ 1,570.00 | Temp door and hasp | $ 1,570.00 | JF1479-028A | |||||
| Carroll County Administration Building | 25108 | Unified Doors and Hardware | 5 R.2 | Accepted | 11/21/2025 | $540.00 | Chisel hinge pocket and install hinges | $540.00 | JF1479-032A | |||||
| Carroll County Administration Building | 25108 | Unified Doors and Hardware | 6 R.2 | Accepted | 11/21/2025 | $1,380.00 | Swap modified temp doors | $1,380.00 | JF1479-032A | |||||
| Carroll County Administration Building | 25108 | Unified Doors and Hardware | 7 | Rejected | 1/5/2026 | $700.00 | Cut down frame | |||||||
| Carroll County Administration Building | 25108 | Unified Doors and Hardware | 8 | Rejected | 1/9/2026 | $80.00 | Install gasketing | |||||||
| Carroll County Administration Building | 25108 | Unified Doors and Hardware | 9 | Accepted | 1/13/2026 | $250.00 | Cut top off door | $250.00 | JF1479-039A | |||||
| Carroll County Administration Building | 25108 | Unified Doors and Hardware | 10 | Pending | 2/27/2026 | $3,500.00 | MOB and removal of existing HW | |||||||
| Carroll County Administration Building | 25108 | Unified Doors and Hardware | 11 | Accepted | 3/2/2026 | $3,360.00 | T&M and bondo work | $3,360.00 | JF1479-045A | |||||
| Carroll County Administration Building | 25108 | Unified Doors and Hardware | 12 | Pending | 3/17/2026 | $11,942.00 | Touch-up T&M | |||||||
| Carroll County Administration Building | 25108 | Unified Doors and Hardware | 13 | Pending | 5/1/2026 | $2,800.00 | Install fail secure locks, kickplates | |||||||
| Carroll County Administration Building | 25108 | Unified Doors and Hardware | 14 R.1 | Pending | 5/26/2026 | $2,617.00 | Swap doors, door adjustments | |||||||
| Rock Nashville | 25110 | Tull Bros | 1 | Accepted | 5/1/2025 | $ 14,350.00 | Hardware schedule changes | This was included in our contract | ||||||
| Rock Nashville | 25110 | Tull Bros | 2 | Rejected | 6/30/2025 | $ 2,400.00 | Magnalocks for three frames | |||||||
| Rock Nashville | 25110 | Tull Bros | 3 | Accepted | 8/28/2025 | $ 16,700.00 | Phase 1-3 scope changes | $ 16,700.00 | 1391.WA | |||||
| Rock Nashville | 25110 | Tull Bros | 4 | Accepted | 9/4/2025 | $3,955.00 | T&M 28.25 additional prep for openings | $3,955.00 | ||||||
| Rock Nashville | 25110 | Tull Bros | 5 | Accepted | 10/22/2025 | $322.00 | T&M 2.3 hours HMF Jamb repair | $322.00 | 1391.3YB | |||||
| Rock Nashville | 25110 | Tull Bros | 6 | Accepted | 10/22/2025 | $532.00 | T&M 3.8 hours inventory | $532.00 | 1391.3YC | |||||
| Rock Nashville | 25110 | Tull Bros | 7 | Accepted | 10/22/2025 | $210.00 | T&M 1.5 hours 133b door removal and reinstall | $210.00 | 1391.3YC | |||||
| Rock Nashville | 25110 | Tull Bros | 8 | Accepted | 10/22/2025 | $427.00 | T&M lockset stud issue | $427.00 | 1391.3YE | |||||
| Rock Nashville | 25110 | Tull Bros | 9 R.1 | Accepted | 10/24/2025 | $2,771.40 | Modify pairs | $2,771.40 | 1391.3YA | |||||
| Rock Nashville | 25110 | Tull Bros | 10 | Accepted | 10/22/2025 | $427.00 | T&M 3.05 troubleshooting incorrect/incompatible HW | $427.00 | 1391.3YF | |||||
| Rock Nashville | 25110 | Tull Bros | 11 | Accepted | 12/2/2025 | $1,100.00 | T&M Modify pairs | $1,100.00 | 1391.3WB | |||||
| Rock Nashville | 25110 | Tull Bros | 12 | Accepted | 12/2/2025 | $1,540.00 | T&M Rework flush bolt preps | $1,540.00 | 1391.3WB | |||||
| Rock Nashville | 25110 | Tull Bros | 13 | Accepted | 12/2/2025 | $2,310.00 | T&M Install harnesses | $2,310.00 | 1391.3WB | |||||
| Rock Nashville | 25110 | Tull Bros | 14 | Accepted | 12/2/2025 | $330.00 | T&M Prep doors | $330.00 | 1391.3WB | |||||
| Rock Nashville | 25110 | Tull Bros | 15 | Accepted | 12/2/2025 | $330.00 | T&M Fill jamb holes | $330.00 | 1391.3WB | |||||
| Rock Nashville | 25110 | Tull Bros | 16 | Accepted | 12/2/2025 | $1,540.00 | T&M Route tops for overhead stops | $1,540.00 | 1391.3WB | |||||
| Rock Nashville | 25110 | Tull Bros | 17 | Accepted | 12/2/2025 | $660.00 | T&M Undercut doors | $660.00 | 1391.3WB | |||||
| Rock Nashville | 25110 | Tull Bros | 18 | Accepted | 12/10/2025 | $940.00 | T&M repair frames | $940.00 | 1391.3RA | |||||
| Rock Nashville | 25110 | Tull Bros | 19 | Accepted | 12/29/2025 | $220.00 | T&M Undercut doors | $220.00 | 1391.3RB | |||||
| Rock Nashville | 25110 | Tull Bros | 20 | Accepted | 12/29/2025 | $110.00 | T&M Cylinder prep | $110.00 | 1391.3RB | |||||
| Rock Nashville | 25110 | Tull Bros | 21 | Accepted | 12/29/2025 | $990.00 | T&M Replaced rosettes | $990.00 | 1391.3RB | |||||
| Rock Nashville | 25110 | Tull Bros | 22 | Accepted | 12/29/2025 | $2,310.00 | T&M Installed missing wire harnesses | $2,310.00 | 1391.3RB | |||||
| Rock Nashville | 25110 | Tull Bros | 23 | Accepted | 1/16/2026 | $220.00 | T&M repair door | $220.00 | 1391.1BMA | |||||
| Rock Nashville | 25110 | Tull Bros | 24 | Accepted | 1/20/2026 | $6,100.00 | Added openings | $6,100.00 | 1391.3A | |||||
| Rock Nashville | 25110 | Tull Bros | 25 | Accepted | 1/21/2026 | $220.00 | T&M Modified exit devices | $220.00 | 1391.3EB | |||||
| Rock Nashville | 25110 | Tull Bros | 26 | Accepted | 1/21/2026 | $2,480.00 | T&M Multipoint lock installation | $2,480.00 | 1391.3EB | |||||
| Rock Nashville | 25110 | Tull Bros | 27 | Accepted | 1/21/2026 | $550.00 | T&M Re-handed hinge preps | $550.00 | 1391.3EB | |||||
| Rock Nashville | 25110 | Tull Bros | 28 | Accepted | 1/21/2026 | $660.00 | T&M Modified auto door bottom preps | $660.00 | 1391.3EB | |||||
| Rock Nashville | 25110 | Tull Bros | 29 | Accepted | 1/21/2026 | $880.00 | T&M Prep door bottoms | $880.00 | 1391.3EB | |||||
| Rock Nashville | 25110 | Tull Bros | 30 | Accepted | 1/21/2026 | $1,100.00 | T&M Form extra wide barn doors | $1,100.00 | 1391.3EB | |||||
| Rock Nashville | 25110 | Tull Bros | 31 | Accepted | 1/29/2026 | $2,750.00 | T&M auto operator track | $2,750.00 | 1391.3EB | |||||
| Rock Nashville | 25110 | Tull Bros | 32 | Accepted | 2/5/2026 | $5,586.00 | Finish work | $5,586.00 | 1391.3EB | |||||
| Rock Nashville | 25110 | Tull Bros | 33 | Pending | 3/9/2026 | $1,760.00 | T&M Opening 300 | |||||||
| Rock Nashville | 25110 | Tull Bros | 34 | Accepted | 3/16/2026 | $1,050.00 | MOB and install thresholds | $1,050.00 | 1391.13DG | |||||
| Rock Nashville | 25110 | Tull Bros | 35 | Pending | 5/8/2026 | $1,500.00 | Pyrotecnico Openings | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 1 | Rejected | 7/14/2025 | $ 26,400.00 | Temp doors | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 1 | Rejected | 7/14/2025 | $ 26,400.00 | Temp doors | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 2 | Rejected | 7/16/2025 | $ 104,164.00 | Frame prep | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 2 | Rejected | 7/16/2025 | $ 104,164.00 | Frame prep | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 3 | Accepted | 7/28/2025 | $11,800.00 | HMF 20 Fasteners Add | $11,800.00 | ||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 3 | Accepted | 7/28/2025 | $11,800.00 | HMF 20 Fasteners Add | $11,800.00 | ||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 4 | Accepted | 7/28/2025 | $2,750.00 | Reinstall HMF removed for Electrician | $2,750.00 | CA1180-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 4 | Accepted | 7/28/2025 | $2,750.00 | Reinstall HMF removed for Electrician | $2,750.00 | CA1180-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 5 | Accepted | 8/4/2025 | $341.33 | Overnight HMF fasteners | $341.33 | CA1180-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 5 | Accepted | 8/4/2025 | $341.33 | Overnight HMF fasteners | $341.33 | CA1180-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 6 | Accepted | 8/21/2025 | $770.00 | Drilling and fishing wire | $770.00 | CA1180-001I and CA1183-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 6 | Accepted | 8/21/2025 | $770.00 | Drilling and fishing wire | $770.00 | CA1180-001I and CA1183-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 7 R.1 | Accepted | 9/8/2025 | $2,800.00 | Added HW to four buildings | $ 2,800.00 | CA1182-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 7 R.1 | Accepted | 9/8/2025 | $2,800.00 | Added HW to four buildings | $ 2,800.00 | CA1182-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 8 | Accepted | 9/2/2025 | $1,120.00 | T&M to remove and reinstall openings | $ 1,120.00 | CA1180-01I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 8 | Accepted | 9/2/2025 | $1,120.00 | T&M to remove and reinstall openings | $ 1,120.00 | CA1180-01I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 9 | Accepted | 9/29/2025 | $870.00 | T&M to remove opening | $ 870.00 | CA1180-01I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 9 | Accepted | 9/29/2025 | $870.00 | T&M to remove opening | $ 870.00 | CA1180-01I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 10 R.1 | Accepted | 10/24/2025 | $9,389.00 | Enlarge dimples for fastener | $9,389.00 | ||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 10 R.1 | Accepted | 10/24/2025 | $9,389.00 | Enlarge dimples for fastener | $9,389.00 | ||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 11 R.1 | Accepted | 11/12/2025 | $660.00 | Indicator lock prep | $660.00 | ||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 11 R.1 | Accepted | 11/12/2025 | $660.00 | Indicator lock prep | $660.00 | ||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 12 | Accepted | 10/17/2025 | Two options for pricing | Door shield installation | $ 6,900.00 | CA1180-01I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 12 | Accepted | 10/17/2025 | Two options for pricing | Door shield installation | $ 6,900.00 | CA1180-01I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 13 | Accepted | 11/10/2025 | $10,550.00 | T&M frame mods | $ 10,550.00 | CA1180-01I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 13 | Accepted | 11/10/2025 | $10,550.00 | T&M frame mods | $ 10,550.00 | CA1180-01I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 14 | Accepted | 11/17/2025 | $350.00 | Correct CVR prep | $350.00 | CA1180-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 14 | Accepted | 11/17/2025 | $350.00 | Correct CVR prep | $350.00 | CA1180-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 15 | Accepted | 11/18/2025 | $350.00 | Prep CVR on door for openings 01.418B | $350.00 | CA1180-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 15 | Accepted | 11/18/2025 | $350.00 | Prep CVR on door for openings 01.418B | $350.00 | CA1180-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 16 | Accepted | 11/21/2025 | $350.00 | Prep door 01.215B | $350.00 | CA1180-0011 | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 16 | Accepted | 11/21/2025 | $350.00 | Prep door 01.215B | $350.00 | CA1180-0011 | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 17 | Accepted | 12/15/2025 | $700.00 | Swing pair | $700.00 | CA1180-01I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 17 | Accepted | 12/15/2025 | $700.00 | Swing pair | $700.00 | CA1180-01I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 18 | Accepted | 1/23/2026 | $300.00 | Removed damaged hardware | $300.00 | CA1180-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 18 | Accepted | 1/23/2026 | $300.00 | Removed damaged hardware | $300.00 | CA1180-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 19 R.2 | Pending | 2/13/2026 | $2,850.00 | Undercut bathroom doors | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 19 R.2 | Pending | 2/13/2026 | $2,850.00 | Undercut bathroom doors | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 20 | Accepted | 2/3/2026 | $700.00 | EPT Prep | $700.00 | CA1183-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 20 | Accepted | 2/3/2026 | $700.00 | EPT Prep | $700.00 | CA1183-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 21 | Pending | 2/19/2026 | $26,000.00 | Egress openings hardware reinstallation | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 21 | Pending | 2/19/2026 | $26,000.00 | Egress openings hardware reinstallation | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 22 | Pending | 2/23/2026 | $700.00 | Jan 202 01.684 EPT cut into frames | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 22 | Pending | 2/23/2026 | $700.00 | Jan 202 01.684 EPT cut into frames | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 23 R.1 | Pending | 3/2/2026 | $2,000.00 | Prepping the frame header | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 23 R.1 | Pending | 3/2/2026 | $2,000.00 | Prepping the frame header | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 24 | Accepted | 3/13/2026 | $300.00 | JAN 200 Broken Handle | $300.00 | CA1180-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 24 | Accepted | 3/13/2026 | $300.00 | JAN 200 Broken Handle | $300.00 | CA1180-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 25 | Accepted | 3/13/2026 | $550.00 | Jan 202 Frame prep | $550.00 | CA1182-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 25 | Accepted | 3/13/2026 | $550.00 | Jan 202 Frame prep | $550.00 | CA1182-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 26 R.1 | Accepted | 3/24/2026 | $1,400.00 | JAN 201 Missing electrical box | $1,400.00 | CA1182-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 26 R.1 | Accepted | 3/24/2026 | $1,400.00 | JAN 201 Missing electrical box | $1,400.00 | CA1182-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 27 R.2 | Accepted | 3/25/2026 | $1,100.00 | JAN 202 Overhead stop prep | $1,100.00 | CA1182-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 27 R.2 | Accepted | 3/25/2026 | $1,100.00 | JAN 202 Overhead stop prep | $1,100.00 | CA1182-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 28 | Pending | 3/24/20226 | $80.00 | JAN 201 Swapping out closer arms | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 28 | Pending | 3/24/20226 | $80.00 | JAN 201 Swapping out closer arms | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 29 | Pending | 3/24/2026 | $80.00 | JAN 203 Swapping out closer arms | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 29 | Pending | 3/24/2026 | $80.00 | JAN 203 Swapping out closer arms | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 30 | Pending | 4/6/2026 | Jan 200 and 203 add bottom rods | ||||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 30 | Pending | 4/6/2026 | Jan 200 and 203 add bottom rods | ||||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 31 | Accepted | 4/23/2026 | $440.00 | Field modify cooridnators | $440.00 | ||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 31 | Accepted | 4/23/2026 | $440.00 | Field modify cooridnators | $440.00 | ||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 32 | Pending | 4/28/2026 | $200.00 | Install sweeps on JAN 202 | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 32 | Pending | 4/28/2026 | $200.00 | Install sweeps on JAN 202 | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 33 | Pending | 4/29/2026 | $100.00 | Install 2 sweeps on JAN 202 | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 33 | Pending | 4/29/2026 | $100.00 | Install 2 sweeps on JAN 202 | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 34 | Accepted | 5/1/2026 | $730.00 | Remove and reinstall hinges | $730.00 | CA1180-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 34 | Accepted | 5/1/2026 | $730.00 | Remove and reinstall hinges | $730.00 | CA1180-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 35 | Accepted | 5/1/2026 | $750.00 | Replace door leaf | $750.00 | CA1180-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 35 | Accepted | 5/1/2026 | $750.00 | Replace door leaf | $750.00 | CA1180-001I | |||||
| Project Alliance | 25113 | Unified Doors and Hardware | 36 | Rejected | 5/4/2026 | $1,740.00 | Replace damaged continuous hinges | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 36 | Rejected | 5/4/2026 | $1,740.00 | Replace damaged continuous hinges | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 37 | Pending | 5/11/2026 | $2,400.00 | 40 astragals installation | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 37 | Pending | 5/11/2026 | $2,400.00 | 40 astragals installation | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 38 | Pending | 5/19/2026 | $4,160.00 | Material pricing | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 38 | Pending | 5/19/2026 | $4,160.00 | Material pricing | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 39 | Pending | 5/21/2026 | $39,380.00 | JAN 200 Prep doors | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 39 | Pending | 5/21/2026 | $39,380.00 | JAN 200 Prep doors | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 40 | Pending | 5/26/2026 | $1,050.00 | VRD top latches for JAN 200-202 | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 40 | Pending | 5/26/2026 | $1,050.00 | VRD top latches for JAN 200-202 | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 41 | Pending | 6/1/2026 | $220.00 | Install sweeps | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 41 | Pending | 6/1/2026 | $220.00 | Install sweeps | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 42 | Pending | 6/3/2026 | $495.00 | Repair frame opening | |||||||
| Project Alliance | 25113 | Unified Doors and Hardware | 42 | Pending | 6/3/2026 | $495.00 | Repair frame opening | |||||||
| Sequoyah Middle and High School | 25116 | Gilbane | 1 | Accepted | 5/1/2025 | $ 4,500.00 | Revision 1 changes | $ 4,500.00 | Rolled into contract | |||||
| Sequoyah Middle and High School | 25116 | Gilbane | 2 | Accepted | 9/17/2025 | $ 1,600.00 | Revision 4 changes | $ 1,600.00 | 2 | |||||
| Sequoyah Middle and High School | 25116 | Gilbane | 3 | Accepted | 10/30/2025 | $ 1,785.00 | FI 184 | $ 1,785.00 | 3 | |||||
| KSU Summit II | 25118 | Arch-I-Tech Doors | 1 | Pending | 2/19/2026 | $ 2,400.00 | Install hinge stops per heading #22 | |||||||
| KSU Summit II | 25118 | Arch-I-Tech Doors | 2 | Pending | 2/26/2026 | $ 500.00 | Correct frame for deadbolt strike | |||||||
| KSU Summit II | 25118 | Arch-I-Tech Doors | 3 | Pending | 3/27/2026 | $ 460.00 | Install 12 floor stops | |||||||
| KSU Summit II | 25118 | Arch-I-Tech Doors | 4 | Accepted | 4/24/2026 | $ 550.00 | Replace #2118 Push exit | $ 550.00 | ||||||
| KSU Summit II | 25118 | Arch-I-Tech Doors | 5 | Pending | 5/12/2026 | $ 750.00 | Drill and install 30 viewers | |||||||
| New Legislative | 25119 | Balfour Beatty | 1 | Accepted | 5/19/2025 | $ 10,890.00 | ASI 2 changes | $ 10,890.00 | 1 | |||||
| New Legislative | 25119 | Balfour Beatty | 2 | Accepted | 7/28/2026 | $ 16,502.00 | Added level | $ 16,502.00 | 1 | |||||
| New Legislative | 25119 | Balfour Beatty | 3 | Pending | 8/12/2025 | $ 1,026.00 | ASI 16 changes | |||||||
| New Legislative | 25119 | Balfour Beatty | 4 | Pending | 4/7/2026 | $ 1,900.00 | ||||||||
| New Legislative | 25119 | Balfour Beatty | 5 | Pending | 4/13/2026 | $ 1,900.00 | RFI 787 changes | |||||||
| New Legislative | 25119 | Balfour Beatty | 6 | Pending | 5/8/2026 | $ 5,500.00 | ASI 17 changes | |||||||
| Lovejoy HS | 25122 | Evergreen Corp | 1 | Accepted | 6/18/2025 | $ - | RFI Changes | $ - | ||||||
| Lovejoy HS | 25122 | Evergreen Corp | 2 | Rejected | 9/18/2025 | $ 16,500.00 | Installation of 11 auto operators | |||||||
| Lovejoy HS | 25122 | Evergreen Corp | 3 R.4 | Pending | 2/6/2026 | $ 9,945.00 | ROM for existing door fit | |||||||
| Lovejoy HS | 25122 | Evergreen Corp | 4 | Pending | 5/15/2026 | $ 11,924.00 | Hardware changes | |||||||
| Fulton Brown County | 25123 | Sovereign Cooper | 1 R.1 | Pending | 3/9/2026 | $ 500.00 | Sumbittal change price increase | |||||||
| Fulton Brown County | 25123 | Sovereign Cooper | 2 R.1 | Accepted | 4/6/2026 | $ 1,200.00 | Swap door and MOB | $ 1,200.00 | 1 | |||||
| Atlanta Fire Station #26 | 25124 | Kelley Bros | 1 | Pending | 4/9/2026 | $ 2,900.00 | Install HM frames | |||||||
| Southern Company Gas | 25120 | Leapley Construction | 1 | Accepted | 8/27/2025 | $ 215.00 | Undercut 8th floor bathrooms | $ 215.00 | 2 | |||||
| Southern Company Gas | 25120 | Leapley Construction | 2 | Accepted | 9/25/2025 | $ 4,575.00 | Lite kits | $ 4,575.00 | 1 | |||||
| Southern Company Gas | 25120 | Leapley Construction | 3 | Accepted | 10/8/2025 | $ 100.00 | Install mag lock on opening 851 | $ 100.00 | 2 | |||||
| Southern Company Gas | 25120 | Leapley Construction | 4 | Accepted | 12/22/2025 | $ 100.00 | Swap lock on opening 505 | $ 100.00 | 2 | |||||
| Southern Company Gas | 25120 | Leapley Construction | 5 | Accepted | 1/7/2026 | 2 options | L01 Credit Union Access controls | $ 550.00 | ||||||
| Southern Company Gas | 25120 | Leapley Construction | 6 R.1 | Accepted | 1/27/2026 | $100.00 | L08 MC/CEO office changes | $ 100.00 | 3 | |||||
| Southern Company Gas | 25120 | Leapley Construction | 7 | Void | 1/12/2026 | $350.00 | Double acting door | |||||||
| Southern Company Gas | 25120 | Leapley Construction | 8 | Accepted | 1/13/2026 | $860.00 | Remove 2 gates in stairwells | $ 860.00 | 6 | |||||
| Southern Company Gas | 25120 | Leapley Construction | 9 | Accepted | 1/14/2026 | $425.00 | Run wiring harness | $ 425.00 | 10 | |||||
| Southern Company Gas | 25120 | Leapley Construction | 10 | Accepted | 2/18/2026 | $1,700.00 | Modify 4 barn doors on 8th floor | $ 1,700.00 | 5 | |||||
| Southern Company Gas | 25120 | Leapley Construction | 11 | Accepted | 3/20/2026 | $150.00 | Insall closer | $ 150.00 | 9 | |||||
| Southern Company Gas | 25120 | Leapley Construction | 12 | Accepted | 3/23/2026 | $1,650.00 | MOB and reinstall 7 locksets | $1,650.00 | 7 | |||||
| Southern Company Gas | 25120 | Leapley Construction | 13 | Accepted | 3/26/2026 | $960.00 | Remove and reinstall push/pull in 16 locations | $960.00 | 7 | |||||
| Southern Company Gas | 25120 | Leapley Construction | 14 | Accepted | 4/17/2026 | $485.00 | Swap out door 220A | $485.00 | 8 | |||||
| Henry Tower 1 | 25130 | JE Dunn | 1 | Accepted | 3/20/2026 | $ 350.00 | Door service call | $ 350.00 | 1 | |||||
| Henry Tower 1 | 25130 | JE Dunn | 2 | Accepted | 4/14/2026 | $ 6,975.00 | Install door protection | $ 6,975.00 | 1 | |||||
| Henry Tower 1 | 25130 | JE Dunn | 3 | Pending | 4/27/2026 | $ (2,500.00) | Remove 513 wall stops | |||||||
| Henry Tower 1 | 25130 | JE Dunn | 4 R.1 | Pending | 5/20/2026 | $ (6,600.00) | Remove kickplate | |||||||
| Henry Tower 1 | 25130 | JE Dunn | 5 | Pending | 5/11/2026 | $ 6,785.00 | ASI 11 pricing | |||||||
| Henry Tower 1 | 25130 | JE Dunn | 6 | Accepted | 6/3/2026 | $ 400.00 | Door Mockup | $ 400.00 | 1 | |||||
| Project Hummingbird | 25131 | Allegheny | 1 R.1 | Pending | 3/24/2026 | $ 6,500.00 | Current submittal changes | |||||||
| Project Hummingbird | 25131 | Allegheny | 2 | Pending | 4/30/2026 | $ 417.15 | Avetta subscription | |||||||
| AWS 078 079 | 25132 | Unified Doors and Hardware | 1 | Pending | 2/27/2026 | $ 650.00 | Added 3.615C | |||||||
| AWS 078 079 | 25132 | Unified Doors and Hardware | 1 | Pending | 2/27/2026 | $ 650.00 | Added 3.615C | |||||||
| AWS 078 079 | 25132 | Unified Doors and Hardware | 2 | Pending | 2/27/2026 | $ 2,900.00 | Level 2 office temp doors | |||||||
| AWS 078 079 | 25132 | Unified Doors and Hardware | 2 | Pending | 2/27/2026 | $ 2,900.00 | Level 2 office temp doors | |||||||
| AWS 078 079 | 25132 | Unified Doors and Hardware | 3 | Pending | 3/6/2026 | $ 82,000.00 | Wire 118 exit devices | |||||||
| AWS 078 079 | 25132 | Unified Doors and Hardware | 3 | Pending | 3/6/2026 | $ 82,000.00 | Wire 118 exit devices | |||||||
| AWS 078 079 | 25132 | Unified Doors and Hardware | 4 | Accepted | 3/18/2026 | $ 1,500.00 | EPT Prep | $ 1,500.00 | 041780 | |||||
| AWS 078 079 | 25132 | Unified Doors and Hardware | 4 | Accepted | 3/18/2026 | $ 1,500.00 | EPT Prep | $ 1,500.00 | 041780 | |||||
| AWS 078 079 | 25132 | Unified Doors and Hardware | 5 | Accepted | 4/3/2026 | $ 869.27 | Forklift rental | $ 869.27 | ||||||
| AWS 078 079 | 25132 | Unified Doors and Hardware | 5 | Accepted | 4/3/2026 | $ 869.27 | Forklift rental | $ 869.27 | ||||||
| AWS 078 079 | 25132 | Unified Doors and Hardware | 6 | Pending | 5/4/2026 | $ 9,000.00 | Priority doors | |||||||
| AWS 078 079 | 25132 | Unified Doors and Hardware | 6 | Pending | 5/4/2026 | $ 9,000.00 | Priority doors | |||||||
| AWS 078 079 | 25132 | Unified Doors and Hardware | 7 | Pending | 5/8/2026 | $ 868.51 | Forklift rental | |||||||
| AWS 078 079 | 25132 | Unified Doors and Hardware | 7 | Pending | 5/8/2026 | $ 868.51 | Forklift rental | |||||||
| AWS 078 079 | 25132 | Unified Doors and Hardware | 8 | Pending | 5/15/2026 | $ 5,250.00 | Undercuts | |||||||
| AWS 078 079 | 25132 | Unified Doors and Hardware | 8 | Pending | 5/15/2026 | $ 5,250.00 | Undercuts | |||||||
| 1221 Grundy St | 25136 | Unified Doors and Hardware | 1 | Accepted | 12/5/2025 | $ 1,050.00 | Model room | $ 1,050.00 | ||||||
| 1221 Grundy St | 25136 | Unified Doors and Hardware | 2 | Pending | 1/20/2026 | $ 17,500.00 | Install 7 openings | |||||||
| 1221 Grundy St | 25136 | Unified Doors and Hardware | 3 | Accepted | 3/12/2026 | $ 600.00 | MOB for 3/12/3026 | $ 600.00 | 6800-04 | |||||
| 1221 Grundy St | 25136 | Unified Doors and Hardware | 4 | Pending | 3/16/2026 | $ 750.00 | RFI 139 | |||||||
| 1221 Grundy St | 25136 | Unified Doors and Hardware | 5 | Pending | 3/30/2026 | $ 2,450.00 | Install exit device | |||||||
| 1221 Grundy St | 25136 | Unified Doors and Hardware | 6 | Pending | 5/4/2026 | $ (800.00) | Remove openings | |||||||
| Chatham County | 25139 | Mullins Building | 1 | Rejected | 11/13/2025 | $ 5,275.00 | Added openings | |||||||
| Wellstar Columbia | 25141 | Turner Construction | 1 | Rejected | 2/2/2026 | $ 5,100.00 | Adding 12 pocket doors | |||||||
| Wellstar Columbia | 25141 | Turner Construction | 2 | Pending | 4/3/2026 | $ 750.00 | Add 2 openings | |||||||
| Wellstar Columbia | 25141 | Turner Construction | 3 | Pending | 4/14/2026 | $ 500.00 | RFI 029 to prep frame 2034 for EPT | |||||||
| PCR 233-238 | 25144 | Skanska | 1 | Accepted | 3/26/2026 | $ 900.00 | CCD Drawing changes | $ 900.00 | 1 | |||||
| Murphey Candler | 25145 | Unified Doors and Hardware | 1 | Accepted | 3/31/2026 | $ 1,000.00 | Survey 27 frames | $ 1,000.00 | 1 | |||||
| Cobb Galleria | 25148 | Unified Doors and Hardware | 1 | Accepted | 12/29/2025 | $ 1,500.00 | Install 5 temp doors | $ 1,500.00 | 1 | |||||
| Cobb Galleria | 25148 | Unified Doors and Hardware | 2 | Accepted | 1/8/2026 | $ 350.00 | Hinges | $ 350.00 | 1 | |||||
| Cobb Galleria | 25148 | Unified Doors and Hardware | 3 | Accepted | 1/9/2026 | $ 4,130.00 | Field survey | $ 4,130.00 | 1 | |||||
| Cobb Galleria | 25148 | Unified Doors and Hardware | 4 | Accepted | 1/13/2026 | $ 200.00 | R2212 undercutting | $ 200.00 | 1 | |||||
| Cobb Galleria | 25148 | Unified Doors and Hardware | 5 | Accepted | 1/20/2026 | $ 775.00 | Modifications | $ 775.00 | 2 | |||||
| Cobb Galleria | 25148 | Unified Doors and Hardware | 6 R.1 | Accepted | 1/26/2026 | $ 945.00 | Additional Frame Survey | $ 945.00 | 2 | |||||
| Cobb Galleria | 25148 | Unified Doors and Hardware | 7 | Accepted | 1/26/2026 | $ 1,050.00 | MOB and temp mortise locks | $ 1,050.00 | 2 | |||||
| Cobb Galleria | 25148 | Unified Doors and Hardware | 8 | Accepted | 2/9/2026 | $ 780.00 | Install closers and kick plates | $ 780.00 | 3 | |||||
| Cobb Galleria | 25148 | Unified Doors and Hardware | 9 | Rejected | 2/25/2026 | $ 1,100.00 | R1256A blank off concealed vertical rod preps | |||||||
| Cobb Galleria | 25148 | Unified Doors and Hardware | 10 | Accepted | 3/20/2026 | $ 1,900.00 | N1026 and N1027 HDW Set Update | $ 1,900.00 | 4 | |||||
| Cobb Galleria | 25148 | Unified Doors and Hardware | 11 | Accepted | 3/27/2026 | $ 1,400.00 | Permanent hardware on temp door | $ 1,400.00 | Allowance | |||||
| Cobb Galleria | 25148 | Unified Doors and Hardware | 12 | Accepted | 3/27/2026 | $ 145.00 | T&M swapping out door | $ 145.00 | 3 | |||||
| Cobb Galleria | 25148 | Unified Doors and Hardware | 13 | Pending | 5/12/2026 | $ 37,500.00 | Bulletin 3 changes | |||||||
| Cobb Galleria | 25148 | Unified Doors and Hardware | 14 | Accepted | 5/20/2026 | $ 1,680.00 | T&M and MOB | $ 1,680.00 | Allowance | |||||
| Cobb Galleria | 25148 | Unified Doors and Hardware | 15 | Pending | 6/1/2026 | $ 5,000.00 | Frame prep rework on 4 openings | |||||||
| GMF & RVR | 25149 | Skanska | 1 | Accepted | 4/24/2026 | $ 700.00 | Remove and reinstall new door and hardware | $ 700.00 | 1 | |||||
| LIving Space Buford | 25150 | Allegheny | 1 | Accepted | 3/19/2026 | $ 3,400.00 | Temp doors and hardware | $ 3,400.00 | 1 | |||||
| LIving Space Buford | 25150 | Allegheny | 2 | Accepted | 3/30/2026 | $ 800.00 | Additional MOB | $ 800.00 | 3 | |||||
| LIving Space Buford | 25150 | Allegheny | 3 | Accepted | 4/28/2026 | $ 5,775.00 | Modify bottom hinges | $ 5,775.00 | 2 | |||||
| LIving Space Buford | 25150 | Allegheny | 4 | Pending | 5/15/2026 | $ 700.00 | Undercuts | |||||||
| LIving Space Buford | 25150 | Allegheny | 5 | Rejected | 5/15/2026 | $ 450.00 | Drill electric hinge holes | |||||||
| LIving Space Buford | 25150 | Allegheny | 6 | Pending | 5/29/2026 | $ 3,050.00 | Replace 4 existing doors | |||||||
| LIving Space Buford | 25150 | Allegheny | 7 | Pending | 6/1/2026 | $ 480.00 | Added door | |||||||
| Project Amplify | 25152 | Tull Bros | 1 | Rejected | 12/18/2035 | $ 35,000.00 | Building 706 addition | |||||||
| Project Amplify | 25152 | Tull Bros | 2 | Rejected | 3/2/2026 | $ 1,900.00 | Amendment 24 | |||||||
| CHM02 | 25153 | UHD Group | 2 | Accepted | 2/10/2026 | $ 753.00 | Install gasketing | $ 753.00 | CA1194-01 | |||||
| CHM02 | 25153 | UHD Group | 3 | Accepted | 2/13/2026 | $ (2,600.00) | Changes per specifications sent 2/12/26 | $ (2,600.00) | CA1194-01 | |||||
| CHM02 | 25153 | UHD Group | 4 | Accepted | 2/27/2026 | $ 8,200.00 | Added openings to scope. 8 slabs total. | $ 8,200.00 | CA1194-01 | |||||
| CHM02 | 25153 | UHD Group | 5 R.1 | Accepted | 3/27/2026 | $ 8,000.00 | Bulletin 02 Revision | $ 8,000.00 | CA1194-01 | |||||
| JAN 105 | 25154 | Tull Bros | 1 | Pending | 3/2/2026 | $ 600.00 | Opening change | |||||||
| JAN 107 | 25155 | Tull Bros | 1 | Pending | 3/2/2026 | $ 600.00 | Opening change | |||||||
| URMC | 26101 | Batson Cook | 1 | Pending | 2/2/2026 | $ 100.00 | Increase from butt hinges | |||||||
| URMC | 26101 | Batson Cook | 2 | Pending | 4/27/2026 | $ 375.00 | Add closers | |||||||
| URMC | 26101 | Batson Cook | 3 | Pending | 4/28/2026 | $ 230.00 | Revision 18 changes | |||||||
| Bells Ferry | 26104 | Unified Doors and Hardware | 1 | Accepted | 5/13/2026 | $ 3,050.00 | Temp doors | $ 3,050.00 | 1 | |||||
| Golden Moon Casino | 26102 | Tull Bros | 1 | Pending | 4/29/2026 | $ 12,430.00 | Add 37 leafs per HW set 14 | |||||||
| Highland College | 26108 | BL Harbert | 1 | Pending | 5/5/2026 | $ 16,500.00 | Cost changes per approved submittals | |||||||
| JAN 204 | 26112 | Tull Bros | 1 | Pending | 4/6/2026 | $ 250.00 | Installation of surface mounted door bottom and threshold | |||||||
| JAN 111 | 26116 | Tull Bros | 1 | Pending | 3/27/0206 | $ 600.00 | Opening change | |||||||
| Cross Church | 26125 | Arch-I-Tech Doors | 1 | Pending | 5/5/2026 | $ 2,000.00 | Price increase due to time of bid and current market | |||||||
| JAN 109 | 26115 | Tull Bros | 1 | Pending | 3/27/2026 | $ 600.00 | Opening change | |||||||
| JAN 204 | 26112 | Tull Bros | 2 | Pending | 5/11/2026 | $ 600.00 | 10 astragals installation | |||||||
| CHM02 | 25153 | UHD Group | 1 | Accepted | 1/8/2026 | $ (11,750.00) | Remove 22 leafs from schedule | $ (11,750.00) | CA1194-01 | |||||